Newry City Flood defences to be completed by 2031-32


The Newry Flood Alleviation Scheme is a long-term project, with Phase Two expected to take between five and seven years to complete, and will include the construction of 3.5km flood defences along Newry River and 1.6km of flood defences along Newry Canal.
By Steve Malone
SEETHROUGH barriers may line along Newry Canal and River as part of the flood defences for the City.
It was the third anniversary of the last devastating flood at the start of the month and Dfl Rivers outlined their proposals at a recent multi-agency flood readiness update hosted by BID.
Members of the Flood Alleviation Group joined representatives from Dfl Rivers, Dfl Roads, NI Water and Newry, Mourne and Down District Council at Custom House in Newry.
The meeting covered preparations for the winter months, coordination between agencies and local businesses and progress on Phase Two of the Newry Flood Alleviation Scheme.
Phase One was completed in 2023, which resulted in the construction of 990 metres of culvert, along with 2000 metres of flood wall and embankment works and two new grille structures.
The Newry Flood Alleviation Scheme is a long-term project, with Phase Two expected to take between five and seven years to complete, and will include the construction of 3.5km flood defences along Newry River and 1.6km of flood defences along Newry Canal.
It was discussed that in order to protect the city from flooding, there would need to be barriers along the river and canal, flow controls, floodgates and temporary barriers and an adjustable weir downstream of the bus station.
It was agreed that a forum should be announced to give local groups an opportunity to contribute.
With winter soon approaching, the agencies outlined their plan, which included flood protection measures being progressed for 32 businesses in Basin Walk and Sugar Island. Businesses are encouraged to highlight town centre drainage hotspots so these can be brought to Dfl Roads’ attention. There will also be a joint training exercise involving agencies, BID and the Newry flood group.
Currently there are 1,199 properties at risk of flooding once in 100-years and 1,165 properties at risk of flooding once in 75-years, floods would come from Newry River, Newry Canal and tributaries.
An option could be to use the canal as flood storage, or as flow conveyance/bypass, upstream storage and weir replacement but the preferred option discussed at the meeting hosted by BID includes a construction of a flow control on the Newry Canal (in the vicinity of the Lock gates). Also a construction of 3.5km flood defences along Newry River, and 1.6km of flood defences along Newry Canal. It is suggested that there is an adjustable weir downstream at Newry Bus Station and the use of demountable and flood gates.
To be 100 percent flood proof it would mean excessive high flood defences, which would lose the river amenity in the city, have a visual impact on the historic setting of Newry and impact on numerous bridge structures and buildings in the city.
Those at the meeting got to see some of the flood barrier designs, which included black cladded flood wall with anti-climb coping, stone clad flood wall with anti-climb coping and solid walls with demountable glass panel.